The need
Rochdale Borough Council had declared a housing emergency. Close to 10,000 households were waiting to be rehoused, and later council papers recorded more than 20,000 people on the waiting list. For young people at risk of homelessness the council needed homes with support on hand, in the borough, close to the communities they knew.
The council had land, the commitment to use it, and access to grant money through the Single Homelessness Accommodation Programme. What it lacked was the capacity to turn a small brownfield site into homes. Brownfield sites bring uncertainty below ground due to having been previously built on and with room for only twelve homes, this site was too small to absorb that risk. Developers and larger registered providers tend to pass sites like this over.
The plan
Scheme H was one of the four sites the council agreed to take forward with Cornerstone Place. The council kept responsibility for getting it right for the people who would live there. Through Cornerstone Place’s Impact First Social Housing® model, we provided the development capacity it did not have, taking the site through planning, making grant applications, managing design and procurement, and managing the build.

We charged a fee for development management much like a quantity surveyor would and took no margin on cost, with every line of expenditure visible to the council throughout. Alongside grant funding from the Single Homelessness Accommodation Programme, with Cornerstone Place’s help, the scheme secured financial support from the Brownfield Fund to meet the extra costs of building on previously developed land.
In line with Cornerstone Place’s Impact First Social Housing® model, on completion Rochdale Borough Council would own the homes for the long term keeping ‘assets in the hands of the impact-makers’.
The build
Scheme H provides twelve self-contained flats for supported living, with staff facilities on site. Outside, there is shared amenity space, secure storage for twelve bicycles and bin storage, set within new landscaping and boundary walls.
The homes are built using modern methods of construction, with a timber frame above block and beam floors, and are designed to be net zero in operation, with roof-mounted solar PV and air source heat pumps. R&M Property Group were our main contractor, with Ward Williams Associates as employer’s agent and quantity surveyor, Triangle Architects as architect, and QED and Soiltechnics advising on structures and foundations.

The challenges
Site investigations revealed the foundations of the building had to be piled. This added some extra time to the project but is a common hurdle and was covered financially by the Brownfield Fund money.
Utility commissioning took longer than expected due to some re-routing by the utility company but because the books were open, the council saw these pressures as they arose and were able to absorb the cost of the delay. On subsequent projects, firmer utility quotes are now always sought before the cost plan is fixed.

The delivery
With the homes a week or two away from handover to Rochdale, the council will be able to hand keys on to twelve young people who will now have a self-contained home of their own in their own community with support on site, and close to the people and services they know.